Evaluation of the in situ disposal test near the Walsoorden sandbar 2006, meer
Monitoring by external contractors of the in situ disposal test near the Walsoorden sandbar 2006, meer
Monitoring by external contractors of the in situ disposal test near the Walsoorden sandbar 2006: continuation, meer
Numerical research on the reshaped tip of the Walsoorden sandbar, meer
Planning of the in situ disposal test near the Walsoorden sandbar 2006, meer
Workshop on results of in situ disposal test near the Walsoorden sandbar 2006, meer
Abstract
In 2006 a second disposal test (500.000 + 900.000 m3) was executed near the Walsoorden sandbar, using the traditional clapping technique to dispose the dredged sediments. An intensive monitoring programme (+ evaluation criteria) were defined based on the experience of the first test. The monitoring consisted of MBES, sediment transport and ecological monitoring. Most of monitoring was performed by external contractors (contracts with Flemish government).
JJP was a member of the steering committee that performed the follow-up of the monitoring and the results.
In 2010 FHR evaluated this second disposal test and organized a workshop where the results were presented.
Alle informatie in het Integrated Marine Information System (IMIS) valt onder het VLIZ Privacy beleid